- N15bn disbursed as part of compensation for Section 1 of the Lagos-Calabar Highway
- Compensation payments to be completed within the next 10 days for all property owners
- Minister Umahi promised transparency and resolve legal issues related to compensation
The Federal Government announced that it had disbursed N15bn out of the N18bn allocated for the first phase of compensation to property owners along Section One of the Lagos-Calabar Highway.
This was disclosed during a stakeholders' meeting in Lagos on Sunday, February 23 regarding the Lagos-Calabar Coastal Highway project.
Obioha announces total compensation exceeding n18bn for Lagos-Calabar highway
Bede Obioha, the Director of Federal Highways, Bridges, and Design at the Federal Ministry of Works, stated that the total compensation amount exceeded N18bn.
He said, “For Section 1, 47.7km, the quantum of compensation already put together is in excess of N18bn, and so far the contractor has managed to disburse over N15bn.
“Section 2 is being put together and as soon as all is done and necessary, we will now make the figure known as well. You will agree with me, we have been very transparent in all we are doing and engaging you as we get along.”
Minister of Works, David Umahi, revealed that 30km of the 70km stretch of the Lagos-Calabar Coastal Highway Phase 1, Section 1, would be inaugurated in May.
He said, “30km out of 70km of Channel Zero, Lagos-Calabar Coastal Highway to be commissioned in May 2025.”
Umahi expresses frustration over compensation process
Recall that in November 2024, it was reported that N18bn had been earmarked to compensate property owners along this section of the highway.
Umahi further assured that all individuals on the compensation list would receive payment within 10 days.
He said, “I wouldn’t have been able to respond if you had asked me this question earlier. But let me say clearly and emphatically that I’m quite frustrated with this situation. However, my hands are tied by the law. I understand that I’ve already lost some properties to arrangements like this.
“It’s incredibly challenging to pay for this, but when facing legal obligations, one is bound to comply. We have engaged professionals to handle this process and the Federal Executive Council approved an initial compensation budget of N8bn for this section, based on the recommendation by the Bureau of Public Procurement.
“But today, we are reaching N18bn, that’s where we are now. I am going to publish all details for transparency, including the names, pictures, dimensions, and costs involved. However, there are over 10 cases related to compensation in court and we will comply with whatever decisions the court makes. We will go to the Supreme Court if necessary to strengthen our democracy and seek final judgment on this matter.”
50% paid, 100% expected within 10 days, Umahi
While discussing the compensation process, Umahi clarified that his ability to provide satisfactory compensation was limited by legal constraints. He emphasised that the compensation was backed by legal principles, following expert consultations.
"Fifty per cent of the compensation has already been paid," he said, adding that he had instructed Olukorede Keisha, the Federal Controller of Works in Lagos State, to proceed with the payments without waiting for additional approvals from the Federal Executive Council, prioritising the interests of those affected.
“Those affected should be able to access their funds for relocation. Therefore, within the next 10 days, we will complete 100 per cent of the payments as documented by our enumerators,” the minister had stated.
Meanwhile, regarding the tax credit given to Dangote Group on the existing Lekki Free Trade Zone, Umahi noted that N10bn would be paid in compensation by mid-March.
“On compensation to those affected at the Eleko Community, what is happening at the community is a beautiful thing, not just the coastal highway, but it comes with tax credit to Dangote, and we are paying about N10bn in compensation from that Lekki Free Trade Zone down to Eleko.
“We will do another engagement before we start paying, maybe by the middle of March, we will start paying the compensation, we would not take anybody’s infrastructure without compensating them.”
Tension rises over Lagos-Calabar coastal road exclusion in 2025 budget
Meanwhile, TheRadar earlier reported that the Lagos-Calabar Coastal Road was said to be missing from the 2025 budget, raising questions about funding and possible impact on other infrastructure projects.
The Lagos-Calabar Coastal Road project had been expected to be funded through a PPP arrangement, but its omission from the budget had left many wondering about its future.