• Ogun State's traffic agency says a temporary diversion at Aseese on the Lagos-Ibadan Expressway, set up so the Federal Ministry of Works and CBC Construction Company can install a pedestrian bridge, runs from Wednesday 18 November to Sunday 22 November 2026.
• The first day of the work left motorists in both directions stuck for hours, with one driver reporting eight hours between Mowe and Magboro, and the Federal Road Safety Corps is now pointing travellers to the Sagamu-Ijebu Ode and Ikorodu-Sagamu routes.
• Thursday morning reports did not agree, with TVC News describing free movement on some sections and BusinessDay reporting traffic from Aseese to Berger, and no agency has said whether the remaining work will move to night hours.
For thousands of people who live in Mowe, Ibafo, Magboro and the estates along the Ogun side of the expressway and work in Lagos, the Lagos-Ibadan Expressway is not one route among many. It is the route. On Wednesday evening, many of them sat in the same spot for hours. Punch reported that some left their vehicles and walked; others paid motorcyclists to take them through back roads.
The cause was a planned diversion at Aseese. The Ogun State Traffic Compliance and Enforcement Agency (TRACE), through its spokesperson Babatunde Akinbiyi, said the Federal Ministry of Works, working with CBC Construction Company, would divert traffic from Wednesday 18 November to Sunday 22 November so a pedestrian bridge could be installed across the expressway. The Whistler quoted the agency as saying the diversion was expected to last four days, although the dates it gave run from Wednesday to Sunday, five days in all. BusinessDay's report on the stranded motorists described the work as a resumption of construction on the bridge.
A diversion to Sunday, starting with the worst day
According to the TRACE statement as reported by Punch, Lagos-bound vehicles are being diverted towards the Lagos carriageway at Aseese and rejoin their normal route at an exit point opposite Christ Embassy. TRACE said its officers and the Federal Road Safety Corps (FRSC) would be on the corridor to manage the flow.
On Wednesday, that arrangement did not hold up against the evening rush. Several outlets, including BusinessDay, Vanguard and TVC News, reported that Lagos-bound traffic backed up from the Redemption Camp area to Aseese bus stop, while Ogun-bound vehicles were held between the Long Bridge area and Aseese. TVC News and P.M. News also reported a crash involving seven vehicles in the early hours of Wednesday, which had already slowed traffic heading towards Ogun State before the evening build-up.
At around 10pm, both sides were still close to a standstill. Part of the reason, according to the same reports, was drivers going against the traffic to escape the queue, which ended up blocking both ends of the road.
How long the trip took, and what it cost
The figure most outlets carried came from a motorist who said the trip from Mowe to Magboro, normally a short hop, took eight hours. Vanguard reported that a commuter who boarded a bus in Ibadan shortly after 11am did not reach Magboro until about 5.30pm.
For people without a car, the extra cost came from motorcycles. BusinessDay and Vanguard reported that commercial motorcyclists carried stranded commuters along side routes at high fares. Punch reported one rider asking for as much as ₦6,000 for a trip from Mowe to Ibafo. That figure comes from a single report and is not a standard rate, but it gives a sense of what a jam like this can add to a day's transport budget.
Among those stuck was Sunday Dare, Special Adviser to President Bola Tinubu on Media and Communications, who said in a Facebook post that he spent more than five hours in the traffic on his way to Ibadan. He questioned why the contractor would "choose the busiest hours of vehicular traffic" and asked why the work was not done during hours "when traffic is lean", according to Vanguard and The Whistler. No response from CBC Construction Company or the Ministry of Works to his comments had been reported at the time of writing.
What FRSC is telling motorists to do
The FRSC Ogun State Command has advised drivers to stay off the affected stretch where they can. Its spokesperson, Afolabi Odunsi, told the News Agency of Nigeria, in a statement carried by Vanguard, that Ibadan-bound motorists should consider the Sagamu-Ijebu Ode route and Lagos-bound motorists the Ikorodu-Sagamu route "where possible".
Odunsi also warned against driving against traffic, saying it worsens congestion and raises the risk of crashes. He said FRSC personnel had been deployed and were working with other security agencies to clear the jam.
Neither alternative is short. Both mean a longer drive and more fuel, and the Ikorodu-Sagamu road carries its own heavy traffic. For commuters who live between Mowe and Magboro, there is no real bypass: their homes sit on the stretch under pressure. The practical options are leaving much earlier or later than usual, working from home where an employer allows it, or travelling outside the evening peak until the diversion ends.
Thursday's reports do not agree
Early Thursday reports pointed in different directions. TVC News, citing updates from the TrafficPalava account on X, reported at 7.46am that vehicles were moving freely from Aseese bus stop through to Iyana-Oworo between about 5.55am and 6.30am, along with stretches such as Berger, 7UP and Alapere. It said the Kara Bridge inward Aseese axis was still blocked. TVC News's Thursday traffic update also linked part of the delay to the continuing rehabilitation of Kara Bridge, which has been slowing traffic on the corridor separately from the Aseese work.
BusinessDay, however, reported that on Thursday morning traffic had extended from Aseese to Berger. The two accounts cover different times and directions, TheRadar has not independently confirmed conditions on the road, and neither settles how the rest of the week will go.
Adeleye Olajide, acting Controller of the Federal Ministry of Works in Ogun State, defended the timing to Punch, saying the bridge has to be launched and that "this is better done now than waiting for the festive period". He did not say, in the reports seen by TheRadar, whether the remaining lifts would be moved to night hours, as Dare and many motorists have asked.
The diversion is scheduled to end on Sunday 22 November, and the questions for the next three days are whether the contractor changes its working hours, whether TRACE and FRSC can stop drivers going against traffic, and whether the end date holds. Anyone travelling between Lagos and Ibadan before Sunday, including for weekend events, is likely to face delays around Aseese and Kara Bridge, and announcements from TRACE and FRSC Ogun are the ones to watch.
Also read: FG shuts section of Eko Bridge Sunday for emergency repairs
Also read: Why Nigerian transport fares remain high despite CNG cost advantage
How long did the Aseese diversion add to your trip this week, and what did it cost you? Tell us in the comments.